Camera IconArdea Resources managing director and chief executive officer Andrew Penkethman​ presenting at a recent nickel conference. Credit: File

Ardea Resources has struck a game-changing and updated joint venture agreement with giants Sumitomo Metal Mining and Mitsubishi Corporation, securing funding and a gold opening at its world-class Kalgoorlie Nickel Project (KNP).

The Japanese consortium will fully fund a $58.8M pre-front-end engineering and design (Pre-FEED) optimisation phase at Goongarrie, lifting its total study commitment to $157.3M and opening the door to a 65 per cent gold interest for Ardea.

The deal delivers another hefty vote of confidence in a project already boasting federal major project status, WA lead agency recognition and a potential $1 billion funding war chest backed by conditional, non-binding support from Export Finance Australia and the US Export-Import Bank. It also features in Australia-Japan and Japan-US critical minerals cooperation frameworks.

In return for footing Ardea’s $29.4M share of the study costs, the Japanese partners have lifted their stake in the project’s parent company, Kalgoorlie Nickel Pty Ltd (KNPL) from 35 to 45 per cent. A positive final investment decision would take them to 60 per cent without further payment. That implies a $294M project valuation and $117.6M for Ardea’s eventual 40 per cent stake.

The deal gives the consortium control over most steering decisions, although both parties must approve any changes to the study scope or budget. It will also have the final say on independently peer-reviewed feasibility reports and has boosted its entitlement to the project’s mixed sulphide precipitate from 75 to 80 per cent.

Read more...

Importantly, Ardea has been able to carve out an exit strategy if it so wishes. From 21 February 2027 until the targeted investment decision, Ardea can force a $68.95M sale of its entire stake, plus subsequent contributions, while protecting its interests against dilution. Its partners hold a higher-priority call option at the greater of an adjustable $112M or discounted fair market value. Both remain subject to conditions and applicable approvals.

Perhaps the cleverest twist is Ardea’s move to ring-fence gold from the nickel joint venture, creating a pathway to control 65 per cent of its economics despite shrinking nickel ownership. The prolific Bardoc Tectonic Zone hosts the Big Four gold deposit immediately east of its nickel namesake.

Under agreements still to be finalised, Ardea would take the reins on gold exploration, footing the first $5 million before costs are split 65:35, with further dilution provisions for any failure to contribute. A separate company could secure exclusive gold mining rights, although nickel-cobalt-scandium development would retain priority and areas containing defined nickel resources would remain off-limits.

The Consortium’s commitment to fund the A$58.8 million Pre-FEED Phase means the Project can focus on optimising the Goongarrie Hub before FEED. The terms of the transaction now provide Ardea with a defined minimum exit value while the Project is optimised.

Ardea Resources managing director and chief executive officer Andrew Penkethman

The optimisation kicks off in December, targeting construction and operating savings through mine design, groundwater and geotechnical studies, metallurgy, infrastructure and renewables.

A definitive feasibility report is slated for late 2027, followed by targeted approval of front-end engineering and design (FEED) by year-end. Any approved study cost overruns will be split 60:40, with dilution provisions for non-payment. Further engineering, debt financing and a final investment decision will hinge on the study’s findings.

Meanwhile, the company aims to secure its Gold Rights Agreement in the first half of 2027, clearing the way for scoping studies and drilling, with results targeted then. Mining rights deed talks follow the later of scoping approval and six months after the agreement starts.

The KNP is a monster, hosting what Ardea describes as Australia’s largest nickel-cobalt resource: 854 million tonnes at 0.71 per cent nickel and 0.045 per cent cobalt, containing 6.1 million tonnes of nickel and 386,000 tonnes of cobalt. Its premium goethite-rich ore supports a potential 40-plus-year operation, according to Ardea’s prefeasibility study.

Goongarrie holds the lion’s share, with 584 million tonnes containing four million tonnes of nickel and a 194.1-million-tonne ore reserve. Just 70km northwest of Kalgoorlie-Boulder, the project has highway, rail and power access, with gas 30km away, and ports at Esperance and Kwinana.

Beyond Goongarrie, Ardea retains full ownership of its Kalpini and Yerilla nickel-cobalt projects near Kalgoorlie, which together boast a substantial 270-million-tonne resource containing more than two million tonnes of nickel.

Adding another kicker, a recent scandium by-product scoping study at the nickel hub delivered a $744M pre-tax net present value, with potential recovery alongside nickel and cobalt to be assessed during engineering.

While its Japanese partners drive nickel development forward, Ardea has carved out a pathway to chase a significant gold prize on the same tenure. With $13.8M in cash and no debt, the company appears well-placed to advance both.

Is your ASX-listed company doing something interesting? Contact: matt.birney@wanews.com.au

Get the latest news from thewest.com.au in your inbox.

Sign up for our emails